Overhaul Completed in Just 30 Days
Sulzer completed an overhaul of three General Electric steam turbines and five Clark compressors for a large ethylene plant in Colombia. Sulzer’s service centers in Texas and Bogotá worked together to inspect and repair the three turbines. Sulzer staff helped the customer with project planning, full commissioning, and testing within a very tight timeframe. The city of ...