Long Term Service Agreements Project - Case Study
We are awarded a long term contract to supply spare parts, component repairs, field engineering services of 9 units for GE Fr6 Gas Turbine in South East Asia. We repair and refurbish Gas Turbine components such as Rotor, Nozzle, Blade, Bucket, Vane, Combustion Liner, Transition Pieces, etc. We also provide technical advisers for commissioning of Gas Turbine during major overhaul and major ...
-
Case Study - Aluto Langano Power Plant Rehabilitation
Aluto Langano, Ethiopia – 2007 The Aluto Langano Geothermal Pilot Plant (ALGPP) is located on the Aluto volcanic complex of the Ethiopian Rift valley, close to the eastern escarpment between Lake Langano and Lake Ziway, some 200 km southeast of Addis Ababa. The Aluto volcanic complex is a young acidic system consisting of domes, lava, and pyroclastic interbeds. The geothermal field was ...