WAGABOX® unit of Saint-Florentin - Project
Saint-Florentin landfill (France) Commissioning: 14th February 2017 70 000 tons of waste per year Biogas: 40-50 % CH4 | 0-3 % O2 | 1 500 ppmv H2S | 5-25 % N2 Distance of the gas grid: 3 kilometers ...
-
WAGABOX® unit of Saint-Maximin - Project
Saint-Maximin landfill (France) Commissioning: 26th June, 2017 200 000 tons of waste per year Biogas: 45-50% CH4 | 0-3% O2 | 7 000 ppmv H2S | 5-20 % N2 Distance of the gas grid: 1.2 kilometer Existing gas ...
-
WAGABOX® unit of Pavie - Project
Pavie landfill (France) Commissioning: 30th May, 2018 40 000 tons of waste per year Biogas: 40-50% CH4 | 0-3% O2 | 500 ppmv H2S | 5-25 % N2 Distance of the gas grid: 3 kilometers Existing gas recovery ...
-
WAGABOX® unit of Saint-Palais - Project
Saint-Palais lanfill (France) Commissioning: 6th november 2018 90 000 tons of waste per year Biogas :40-50% CH4 | 0-3% O2 | 1 000 ppmv H2S | 5-20 % N2 Distance of the gas grid: 1.6 kilometer Existing gas ...
-
WAGABOX® unit of Gueltas - Project
Gueltas landfill (France) Commissioning: 13th november 2018 200 000 tons of waste per year Biogas :45-50 % CH4 | 0-5 % O2 | 1 000 ppmv H2S | 5-20 % N2 Distance of the gas grid: 6 kilometers Existing gas ...