Major Steam Turbine Rehabilitations
From Other Products
In the last years, Franco Tosi Meccanica has consistently delivered to the market important projects on a global scale
-
Most popular related searches
2011 A2A, Bergamo, Italy, 11.7 MW
- 2011 A2A, Bergamo, Italy, 11.7 MW
- 2011 CTM Mendoza, Argentina, 60 MW
- 2008 Cons. Turbigo 800, Italy, 320 MW
- 2007 Enel, Fusina, Italy, 160 MW
- 2006 Enel, La Spezia, Italy, 600 MW
- 2006 Consorzio Piacenza 800, Italy, 320 MW
- 2005 EUAS, Seytomer, Turkey, 150 MW
- 2005 ERG, Priolo Sud, Italy, 25 MW
- 2005 Enel, Brindisi, Italy, 660 MW
- 2005 Enel, Porto Tolle, Italy, 660 MW
2011 A2A, Bergamo, Italy 11.7 MW
Project Description: steam turbines rehabilitation, plant partial modification with district heating introduction, heat exchangers supply, thermal mechanical engineering. Scope of Work: Engineering, Supply, Transportation, Erection, Commissioning, Start-Up.
2011 CTM Mendoza, Argentina 60.0 MW
Project Description: steam turbines and generator rehabilitation, supply of new control system, substitution of speed regulation, thermal mechanical engineering, service activities. Scope of Work: Engineering, Supply, Transportation, Erection, Commissioning, Start-Up.