PROJECT
19 off containerised Allburn 3 Incinerators
World Health Organisation—Ethiopia
PROJECT DESCRIPTION
Top loaded, diesel fired, low capacity incinera-tors, factory -installed within 20’ ISO shipping containers, for the disposal of bagged general/clinical waste from hospital and clinics, animal and industrial waste. To be utilised in various lo-cations throughout Ethiopia. Complete with lighting, ventilation, fire protection, access doors, fuel storage tanks and piping.
SCOPE OF OUR SUPPLY
19 identical units comprising;
- Fixed hearth, refractory lined primary com-bustion chamber with diesel fired ignition burner
- Refractory lined secondary chamber with diesel fired afterburner providing 2 seconds residence time
- Combustion air supply fan and distribution system
- Control panel and electrical wiring
- Stainless steel chimney to a height of 5m
- 110% capacity bunded double skin diesel storage tank with fuel delivery pipework
- All mounted within a 20’ ISO shipping container with lighting, ventilation, fire security, three access doors and chimney penetration with weather seal
- Full factory commissioning including re-fractory curing
- Full O&M manuals
- Counterbalanced large profile vertical load-ing door offers safe, reliable loading of waste.
- 1600°C cast refractory lining ensure years of operation with no need for refractory maintenance
- Safety interlocks on doors prevent opening whilst in operation
- Large profile raking door allows for swift Raking resulting in minimal downtime be-tween burn cycles
- Manual slide damper on ash door allows simple control of additional process air as required.
Containerisation of each unit offers;
- Secure means of transportation
- Secure shelter within which the unit can be operated
- Self-contained - Fuel storage and delivery pipework installed (we can also install a generator for the electrical supply)
PROJECT MANAGEMENT AND THE FUTURE
Due to the tight deadline of this project, it was essential to ensure we were not complacent about the size and simplicity of these units. We approach all projects, big and small, in the same professional manner maintaining a programme of works and regular progress meetings between departments to ensure no delays occur.
Matthews Environmental Solutions have worked with The World Health Organisation on a number of occasions. We consider their repeat orders as a sign of the quality of the product we supply and very much look forward to their next enquiry.
-
Most popular related searches
Customer comments
No comments were found for Case study - Allburn Incinerators. Be the first to comment!