Facts :

A large European system operator must connect 9 MW of new wind power on its 63 kV grid.

Contraints :

Building a new HV line will cost € 24 M with a 5-year delivery time.

Ampacimon solution:

ADR Sense was installed in 3 months, allowing a 50% increase in capacity, thus avoiding line congestion.

Typical example: Ampacimon allows optimised use of existing lines in case of grid integration of renewable sources.