Facts :
A large European system operator must connect 9 MW of new wind power on its 63 kV grid.
Contraints :
Building a new HV line will cost € 24 M with a 5-year delivery time.
Ampacimon solution:
ADR Sense was installed in 3 months, allowing a 50% increase in capacity, thus avoiding line congestion.
Typical example: Ampacimon allows optimised use of existing lines in case of grid integration of renewable sources.