Delorean’s Engineering Division (formerly Biogass Renewables)

Jandakot Bioenergy Plant - Case Study

SHARE
Oct. 31, 2013

Biogass Renewables undertook the development, design, finance, build, commission and operational support for the Jandakot Bioenergy Plant – processing Australian Commercial and industrial organic waste streams to power generation, Biogass Renewables handled all, approvals from planning to DER (EPA) including grid connection and sale of the renewable power generated on site. 

Most popular related searches
  • Location  Jandakot, Perth, WA
  • Start Date   November 2013
  • Completion Date Completion Date
  • Client  Richgro Garden Products
  • Value $8-10m
  • Richgro receive 35,000 – 50,000 tonnes per annum of food waste from new waste producers in the region
  • Richgro have been enabled to receive higher revenue waste streams from contaminated organic waste
  • The facility can produce over 2MW of baseline electricity with 1.7MW exported to the local grid
  • The facility has eliminated previous electricity costs from energy retailers of circa $400,000+ / annum
  • The facility outputs a bio-fertiliser to blend with existing Richgro products, improving nutritional and breakdown characteristics
  • Commissioned in 2015.
  • Sub – 4-year payback on capital (before grants etc.).