In 2004, Brookfield installed a new minimum flow turbine at its Sherman Island hydroelectric power facility, located on the Hudson River in Queensbury, NY. CHC provided a 1250 mm axial flow turbine for the new powerplant with a 1250 kW/514 RPM synchronous generator. The new plant can produce up to 1.25 MW of power.
PROJECT FACTS
- 1.25 MW Plant Capacity
- 1250 mm Axial Flow Propelle
- Net Head 16.55 m (54 ft)
- 1242 kW Output
- Commissioned 2004